United States › Grid › Interconnection queues › Indiana
SOLAR · PJMHoosier Line Solar
Hoosier Line Solar is a 180 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in White County, Indiana, connecting to AEP.
Queue statusConsented
- PlanningQueued Sep 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AF1-207
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Reynolds-Olive #1 345 kV
- Location
- White County, Indiana
- Technology
- Solar: 180 MW
- Total requested
- 180 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 27 September 2019
- Proposed online date
- September 2027
Location
Marker shows the centre of White County; the queue data does not give exact sites.
Other requests in White County
- Honey Creek SolarSolar + storage · 200 MW · agreement signed
- Black Prairie Solar ParkSolar · 200 MW · agreement signed
- Solar project J1482, White CountySolar · 150 MW · agreement signed
- Battery storage project J2496, White CountyBattery storage · 400 MW · in study
- Battery storage project J2663, White CountyBattery storage · 200 MW · in study
- Solar project J1772, White CountySolar · 200 MW · in study
- Battery storage project J3691, White CountyBattery storage · 200 MW · in study
- Solar project J2353, White CountySolar · 190 MW · in study
- Battery storage project J3688, White CountyBattery storage · 150 MW · in study
- Battery storage project J2657, White CountyBattery storage · 138 MW · in study
- Solar project J3168, White CountySolar · 120 MW · in study
- Solar project AG2-491, White CountySolar · 100 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem