Solar + storage project IC-839, Sumter County

Solar + storage project IC-839, Sumter County is a 200 MW solar + storage request with a signed interconnection agreement in the Southeast interconnection queue, in Sumter County, Georgia, connecting to Southern Company.

Queue statusConsented
  1. PlanningQueued Nov 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IC-839
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
North Americus - Palmyra 230 kV Line
Location
Sumter County, Georgia
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Active
Entered queue
15 November 2019
Proposed online date
July 2027

Location

Marker shows the centre of Sumter County; the queue data does not give exact sites.