Solar project IC-447, Sumter County

Solar project IC-447, Sumter County is a 152 MW solar request withdrawn in the Southeast interconnection queue, in Sumter County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandonedApr 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-447
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
North Americus Substation 230 kV bus
Location
Sumter County, Georgia
Technology
Solar: 152 MW
Total requested
152 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
25 March 2016
Withdrawn
April 2016

Location

Marker shows the centre of Sumter County; the queue data does not give exact sites.