Solar project IC-695, Sumter County

Solar project IC-695, Sumter County is a 250 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Sumter County, Georgia, connecting to Southern Company.

Queue statusConsented
  1. PlanningQueued May 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IC-695
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Fortson - North Tifton 500 kV Line
Location
Sumter County, Georgia
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
3 May 2018
Proposed online date
April 2023

Location

Marker shows the centre of Sumter County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Sumter County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem