United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 70

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 70 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AI1-134, Grant County
Solar + storage
200 MWIn study Grant, INPJM Sep 2022target 2029
Solar + storage project Company MK, Lyon County
Solar + storage
200 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Solar project J3859, Branch County
Solar
200 MWIn study Branch, MIMISO Dec 2024target 2028
Battery storage project GI-RSC-2025-02, Moffat County
Battery storage
200 MWIn study Moffat, COWest Jul 2025target 2029
Battery storage project J2840, Olmsted County
Battery storage
200 MWIn study Olmsted, MNMISO Sep 2022target 2025
Other project 110, Pima County
Other · TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Solar project GEN-2024-229, Wilbarger County
Solar
200 MWIn study Wilbarger, TXSPP Mar 2025target 2030
Battery storage project AH2-102, Franklin County
Battery storage
200 MWIn study Franklin, VAPJM Jan 2022target 2026
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Feather Dalea BESS
Battery storage · RWE Clean Energy Development, LLC
200 MWIn study Glasscock, TXERCOT Oct 2024target 2027
Solar project J1576, Washington Parish County
Solar
200 MWAgreement signed Washington Parish, LAMISO Mar 2022target 2026
Solar + storage project Q355, Maricopa County
Solar + storage
200 MWPaused / redesign Maricopa, AZWest Sep 2020target 2023
Desert Rose Solar
Solar
200 MWPaused / redesign Andrews, TXERCOT Jun 2018
Solar project J1629, Columbia County
Solar
200 MWAgreement signed Columbia, WIMISO Jun 2020target 2027
Battery storage project AH2-378A, Gloucester County
Battery storage
200 MWIn study Gloucester, NJPJM Mar 2022target 2025
Battery storage project GEN-2018-025, Washington County
Battery storage
200 MWPaused / redesign Washington, NESPP May 2018target 2028
Solar project IC-1195, Warren County
Solar
200 MWAgreement signed Warren, GASoutheast Oct 2023target 2028
Solar project J3719, Miami County
Solar
200 MWIn study Miami, INMISO Mar 2024target 2028
Solar + storage project AH2-043, Kanawha County
Solar + storage
200 MWIn study Kanawha, WVPJM Nov 2021target 2025
PSE Chihuahua TX Storage
Battery storage · PureSky Development Inc
200 MWIn study Hidalgo, TXERCOT Dec 2022target 2027
Solar project J1481, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2025
Tendril
Solar + storage
200 MWIn study Kern, CACAISO Apr 2023target 2031
Solar project IC-1204, Jefferson County
Solar
200 MWAgreement signed Jefferson, GASoutheast Nov 2023target 2028
Surplus; J1434
Battery storage
200 MWIn study St. Francis, ARMISO Jun 2025target 2027
Solar project J1196, Sanilac County
Solar
200 MWAgreement signed Sanilac, MIMISO Apr 2019target 2025
Battery storage project GI-SISS-2025-03, Mckinley County
Battery storage
200 MWIn study Mckinley, NMWest Jul 2025target 2027
Onshore wind project J2250, Stutsman County
Onshore wind
200 MWIn study Stutsman, NDMISO Nov 2021target 2024
Solar project J2526, Red River Parish County
Solar
200 MWIn study Red River Parish, LAMISO Sep 2022target 2026
Solar + storage project J3080, Pulaski County
Solar + storage
200 MWIn study Pulaski, ILMISO Sep 2022target 2025
Other project GEN-2023-059, Harrison County
Other
200 MWIn study Harrison, TXSPP Sep 2023target 2029
Solar project 3RSC-2023-01, Pueblo County
Solar
200 MWIn study Pueblo, COWest May 2023target 2025
Battery storage project 17-067, Multnomah County
Battery storage
200 MWAgreement signed Multnomah, ORWest Sep 2017target 2031
Solar project J1107, Cape Girardeau County
Solar
200 MWUnder construction Cape Girardeau, MOMISO Mar 2018target 2023
Solar + storage project AH2-363, Kankakee County
Solar + storage
200 MWIn study Kankakee, ILPJM Mar 2022target 2027
Battery storage project J3169, Hardin County
Battery storage
200 MWIn study Hardin, TXMISO Sep 2022target 2026
Merlin Storage
Battery storage
200 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Solar project AH1-151, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2025
Solar + storage project J1642, Spencer County
Solar + storage
200 MWIn study Spencer, INMISO Feb 2022target 2023
Onshore wind project J1926, Tazewell County
Onshore wind
200 MWIn study Tazewell, ILMISO Mar 2022target 2025
Battery storage project Company NJ, Storey County
Battery storage
200 MWAgreement signed Storey, NVWest Mar 2022target 2026
Solar + storage project Company OB, Churchill County
Solar + storage
200 MWPaused / redesign Churchill, NVWest Sep 2022target 2030
Battery storage project GEN-2022-144, Jackson County
Battery storage
200 MWIn study Jackson, MOSPP Feb 2023target 2030
Solar project 5RSC-2024-23, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jan 2024target 2028
Solar + storage project 710, Ada County
Solar + storage
200 MWIn study Ada, IDWest Mar 2023target 2026
Solar + storage project J4134, Ouachita County
Solar + storage
200 MWIn study Ouachita, ARMISO Oct 2025target 2030
Other project Q605, Maricopa County
Other
200 MWIn study Maricopa, AZWest May 2025target 2031
Solar project Q230, Navajo County
Solar
200 MWUnder construction Navajo, AZWest Sep 2015target 2021
Solar project IC-1180, Jones County
Solar
200 MWPaused / redesign Jones, MSSoutheast Oct 2023target 2028
Battery storage project GI-2011-2 & 7, Arapahoe County
Battery storage
200 MWPaused / redesign Arapahoe, COWest Sep 2022target 2025
Battery storage project J2472, Sullivan County
Battery storage
200 MWIn study Sullivan, INMISO Sep 2022target 2027
Page 70 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)