SOLAR + STORAGE · WEST

Solar + storage project 710, Ada County

Solar + storage project 710, Ada County is a 200 MW solar + storage request in interconnection study in the West interconnection queue, in Ada County, Idaho, connecting to Idaho Power Company.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
710
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
DRAM–RTSN 230kV Line
Location
Ada County, Idaho
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Cluster Study
Queue status
Active
Entered queue
24 March 2023
Proposed online date
June 2026

Location

Marker shows the centre of Ada County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Ada County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem