United States › Grid › Interconnection queues › Idaho
SOLAR + STORAGE · WESTSolar + storage project 665, Ada County
Solar + storage project 665, Ada County is a 400 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Ada County, Idaho, connecting to Idaho Power Company.
Queue statusConsented
- PlanningQueued Aug 2022 (completed)
- ConsentedApr 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 665
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Developer
- Blacks Creek Energy Center, LLC
- Connection point (POI)
- BOBN–Hubbard 230kV Line
- Location
- Ada County, Idaho
- Technology
- Solar: 400 MW · Battery
- Total requested
- 400 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 16 August 2022
- Agreement signed
- 4 April 2024
- Proposed online date
- June 2027
Location
Marker shows the centre of Ada County; the queue data does not give exact sites.
Other requests in Ada County
- Solar + storage project 669, Ada CountySolar + storage · 200 MW · agreement signed
- Battery storage project 639, Ada CountyBattery storage · 150 MW · agreement signed
- Solar project 588, Ada CountySolar · 125 MW · agreement signed
- Solar + storage project 793, Ada CountySolar + storage · 250 MW · in study
- Solar + storage project 710, Ada CountySolar + storage · 200 MW · in study
- Solar + storage project 786, Ada CountySolar + storage · 199 MW · in study
- Solar + storage project 716, Ada CountySolar + storage · 150 MW · in study
- Solar + storage project 708, Ada CountySolar + storage · 150 MW · in study
- Solar + storage project 773, Ada CountySolar + storage · 130 MW · in study
- Battery storage project 767, Ada CountyBattery storage · 50.0 MW · in study
- Battery storage project 640, Ada CountyBattery storage · 150 MW · suspended
- Solar project 567, Ada CountySolar · 200 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem