🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Idaho

SOLAR + STORAGE · WEST

Solar + storage project 665, Ada County

Solar + storage project 665, Ada County is a 400 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Ada County, Idaho, connecting to Idaho Power Company.

Queue statusConsented
  1. PlanningQueued Aug 2022 (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
665
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Developer
Blacks Creek Energy Center, LLC
Connection point (POI)
BOBN–Hubbard 230kV Line
Location
Ada County, Idaho
Technology
Solar: 400 MW · Battery
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
16 August 2022
Agreement signed
4 April 2024
Proposed online date
June 2027

Location

Marker shows the centre of Ada County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Ada County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem