BATTERY STORAGE · SPPBattery storage project GEN-2018-025, Washington County
Battery storage project GEN-2018-025, Washington County is a 200 MW battery storage request suspended in the SPP interconnection queue, in Washington County, Nebraska, connecting to OPPD.
Queue statusPaused / redesign
- PlanningQueued May 2018 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2018-025
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Fort Calhoun 345kV Substation
- Location
- Washington County, Nebraska
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SUSPENSION
- Queue status
- Suspended
- Entered queue
- 29 May 2018
- Proposed online date
- November 2028
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Solar project GEN-2020-078, Washington CountySolar · 100 MW · agreement signed
- Other project GEN-2025-SR24, Washington CountyOther · 200 MW · in study
- Nuclear project GEN-2004-002O, Washington CountyNuclear · 48.0 MW · built
- Battery storage project GEN-2018-090, Washington CountyBattery storage · 125 MW · withdrawn
- Nuclear project GEN-2007-030O, Washington CountyNuclear · 67.0 MW · withdrawn
- Battery storage project GEN-2019-072, Washington CountyBattery storage · 50.0 MW · withdrawn