🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nebraska

SOLAR · SPP

Solar project GEN-2020-078, Washington County

Solar project GEN-2020-078, Washington County is a 100 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Washington County, Nebraska, connecting to OPPD.

Queue statusConsented
  1. PlanningQueued Apr 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2022 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2020-078
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OPPD
Connection point (POI)
Substation 1226 to Substation 1237, 161kV Tap
Location
Washington County, Nebraska
Technology
Solar: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
30 April 2020
Proposed online date
November 2022

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem