United States › Grid › Interconnection queues › Nebraska
OTHER · SPPOther project GEN-2025-SR24, Washington County
Other project GEN-2025-SR24, Washington County is a 200 MW other request in interconnection study in the SPP interconnection queue, in Washington County, Nebraska, connecting to OPPD.
Queue statusIn planning
- PlanningQueued Jun 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2025-SR24
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Fort Calhoun 345kV Substation
- Location
- Washington County, Nebraska
- Technology
- Other: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 12 June 2025
- Proposed online date
- November 2028
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Solar project GEN-2020-078, Washington CountySolar · 100 MW · agreement signed
- Battery storage project GEN-2018-025, Washington CountyBattery storage · 200 MW · suspended
- Nuclear project GEN-2004-002O, Washington CountyNuclear · 48.0 MW · built
- Battery storage project GEN-2018-090, Washington CountyBattery storage · 125 MW · withdrawn
- Nuclear project GEN-2007-030O, Washington CountyNuclear · 67.0 MW · withdrawn
- Battery storage project GEN-2019-072, Washington CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem