🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

Battery storage project AH2-102, Franklin County

Battery storage project AH2-102, Franklin County is a 200 MW battery storage request in interconnection study in the PJM interconnection queue, in Franklin County, Virginia, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Jan 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-102
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Blaine - Roanoke 138 kV
Location
Franklin County, Virginia
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
31 January 2022
Proposed online date
May 2026

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem