United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1196, Sanilac County

Solar project J1196, Sanilac County is a 200 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Sanilac County, Michigan, connecting to ITC MIDWEST.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedOct 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1196
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Greenwood - Rapson (Banner) 345 kV Line Tap
Location
Sanilac County, Michigan
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Active
Entered queue
25 April 2019
Agreement signed
31 October 2022
Proposed online date
August 2025

Location

Marker shows the centre of Sanilac County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Sanilac County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem