🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1944, Sanilac County

Solar project J1944, Sanilac County is a 185 MW solar request in interconnection study in the MISO interconnection queue, in Sanilac County, Michigan, connecting to ITC.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1944
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC
Connection point (POI)
GREENWOOD - RAPSON (BANNER) 345.0kV
Location
Sanilac County, Michigan
Technology
Solar: 185 MW
Total requested
185 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
23 August 2021
Proposed online date
November 2023

Location

Marker shows the centre of Sanilac County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Sanilac County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem