ONSHORE WIND Β· MISO

Onshore wind project J308, Sanilac County

Onshore wind project J308, Sanilac County is a 301 MW onshore wind request withdrawn in the MISO interconnection queue, in Sanilac County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2013 (completed)
  2. Withdrawn / abandonedNov 2019 (project stopped here)
  3. ConsentedJul 2016 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J308
Grid region
MISO (Midcontinent)
Connection point (POI)
ITC Rapson-Banner 345kV Line
Location
Sanilac County, Michigan
Technology
Wind: 301 MW
Total requested
301 MW
Study phase
Int FaS
Queue status
Withdrawn
Entered queue
18 November 2013
Agreement signed
6 July 2016
Proposed online date
October 2016
Withdrawn
November 2019

Location

Marker shows the centre of Sanilac County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Sanilac County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem