🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

BATTERY STORAGE · MISO

Battery storage project J3977, Sanilac County

Battery storage project J3977, Sanilac County is a 250 MW battery storage request in interconnection study in the MISO interconnection queue, in Sanilac County, Michigan, connecting to ITC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3977
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC
Connection point (POI)
GREENWOOD - RAPSON 345.0kV
Location
Sanilac County, Michigan
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
31 March 2025
Proposed online date
June 2029

Location

Marker shows the centre of Sanilac County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Sanilac County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem