SOLAR + STORAGE · MISOSolar + storage project J1642, Spencer County
Solar + storage project J1642, Spencer County is a 200 MW solar + storage request in interconnection study in the MISO interconnection queue, in Spencer County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.
- PlanningQueued Feb 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2023 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1642
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
- Connection point (POI)
- North East (Castle) - Culley 138kV
- Location
- Spencer County, Indiana
- Technology
- Solar: 200 MW · Battery
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 17 February 2022
- Proposed online date
- October 2023
Location
Marker shows the centre of Spencer County; the queue data does not give exact sites.
Other requests in Spencer County
- Solar project J783, Spencer CountySolar · 70.0 MW · under construction
- Gas project AG2-072, Spencer CountyGas · 700 MW · in study
- Solar project J759, Spencer CountySolar · 70.0 MW · built
- Rockport Unit #1Coal · 36.0 MW · built
- Rockport Unit 1Coal · 20.0 MW · built
- Solar + storage project AE1-214, Spencer CountySolar + storage · 800 MW · withdrawn
- Solar + storage project AE2-130, Spencer CountySolar + storage · 800 MW · withdrawn
- Solar + storage project AF2-353, Spencer CountySolar + storage · 800 MW · withdrawn
- Solar project J3721, Spencer CountySolar · 200 MW · withdrawn
- Onshore wind project J1835, Spencer CountyOnshore wind · 200 MW · withdrawn
- Solar + storage project J2960, Spencer CountySolar + storage · 150 MW · withdrawn
- Solar project AC1-040, Spencer CountySolar · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem