Solar + storage project J1642, Spencer County

Solar + storage project J1642, Spencer County is a 200 MW solar + storage request in interconnection study in the MISO interconnection queue, in Spencer County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.

Queue statusIn planning
  1. PlanningQueued Feb 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1642
Grid region
MISO (Midcontinent)
Utility / transmission owner
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Connection point (POI)
North East (Castle) - Culley 138kV
Location
Spencer County, Indiana
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
17 February 2022
Proposed online date
October 2023

Location

Marker shows the centre of Spencer County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Spencer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem