United States › Grid › Interconnection queues › Indiana
SOLAR · MISOSolar project J783, Spencer County
Solar project J783, Spencer County is a 70.0 MW solar request under construction in the MISO interconnection queue, in Spencer County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc..
Queue statusUnder construction
- PlanningQueued Nov 2016 (completed)
- ConsentedJul 2019 (completed)
- Construction (current stage)
- OperatingTarget Apr 2021 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J783
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc.
- Connection point (POI)
- Grandview Sub
- Location
- Spencer County, Indiana
- Technology
- Solar: 70.0 MW
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 14 November 2016
- Agreement signed
- 24 July 2019
- Proposed online date
- April 2021
Location
Marker shows the centre of Spencer County; the queue data does not give exact sites.
Other requests in Spencer County
- Gas project AG2-072, Spencer CountyGas · 700 MW · in study
- Solar + storage project J1642, Spencer CountySolar + storage · 200 MW · in study
- Solar project J759, Spencer CountySolar · 70.0 MW · built
- Rockport Unit #1Coal · 36.0 MW · built
- Rockport Unit 1Coal · 20.0 MW · built
- Solar + storage project AE1-214, Spencer CountySolar + storage · 800 MW · withdrawn
- Solar + storage project AE2-130, Spencer CountySolar + storage · 800 MW · withdrawn
- Solar + storage project AF2-353, Spencer CountySolar + storage · 800 MW · withdrawn
- Solar project J3721, Spencer CountySolar · 200 MW · withdrawn
- Onshore wind project J1835, Spencer CountyOnshore wind · 200 MW · withdrawn
- Solar + storage project J2960, Spencer CountySolar + storage · 150 MW · withdrawn
- Solar project AC1-040, Spencer CountySolar · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem