United States βΊ Grid βΊ Interconnection queues βΊ Indiana
COAL Β· PJMRockport Unit 1
Rockport Unit 1 is a 20.0 MW coal request built and operating in the PJM interconnection queue, in Spencer County, Indiana, connecting to AEP.
Request details
- Queue ID
- R97
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Rockport 765kV
- Location
- Spencer County, Indiana
- Technology
- Coal: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 31 January 2007
- Proposed online date
- November 2011
- Came online
- November 2011
Location
Marker shows the centre of Spencer County; the queue data does not give exact sites.
Other requests in Spencer County
- Solar project J783, Spencer CountySolar Β· 70.0 MW Β· under construction
- Gas project AG2-072, Spencer CountyGas Β· 700 MW Β· in study
- Solar + storage project J1642, Spencer CountySolar + storage Β· 200 MW Β· in study
- Solar project J759, Spencer CountySolar Β· 70.0 MW Β· built
- Rockport Unit #1Coal Β· 36.0 MW Β· built
- Solar + storage project AE1-214, Spencer CountySolar + storage Β· 800 MW Β· withdrawn
- Solar + storage project AE2-130, Spencer CountySolar + storage Β· 800 MW Β· withdrawn
- Solar + storage project AF2-353, Spencer CountySolar + storage Β· 800 MW Β· withdrawn
- Solar project J3721, Spencer CountySolar Β· 200 MW Β· withdrawn
- Onshore wind project J1835, Spencer CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar + storage project J2960, Spencer CountySolar + storage Β· 150 MW Β· withdrawn
- Solar project AC1-040, Spencer CountySolar Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem