ONSHORE WIND Β· MISOOnshore wind project J1835, Spencer County
Onshore wind project J1835, Spencer County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Spencer County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedSep 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1835
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
- Connection point (POI)
- Culley to Grandview 138 KV line tap
- Location
- Spencer County, Indiana
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 25 June 2020
- Proposed online date
- June 2023
- Withdrawn
- September 2024
Location
Marker shows the centre of Spencer County; the queue data does not give exact sites.
Other requests in Spencer County
- Solar project J783, Spencer CountySolar Β· 70.0 MW Β· under construction
- Gas project AG2-072, Spencer CountyGas Β· 700 MW Β· in study
- Solar + storage project J1642, Spencer CountySolar + storage Β· 200 MW Β· in study
- Solar project J759, Spencer CountySolar Β· 70.0 MW Β· built
- Rockport Unit #1Coal Β· 36.0 MW Β· built
- Rockport Unit 1Coal Β· 20.0 MW Β· built
- Solar + storage project AE1-214, Spencer CountySolar + storage Β· 800 MW Β· withdrawn
- Solar + storage project AE2-130, Spencer CountySolar + storage Β· 800 MW Β· withdrawn
- Solar + storage project AF2-353, Spencer CountySolar + storage Β· 800 MW Β· withdrawn
- Solar project J3721, Spencer CountySolar Β· 200 MW Β· withdrawn
- Solar + storage project J2960, Spencer CountySolar + storage Β· 150 MW Β· withdrawn
- Solar project AC1-040, Spencer CountySolar Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem