United States › Grid › Interconnection queues › Nevada
BATTERY STORAGE · WESTBattery storage project Company NJ, Storey County
Battery storage project Company NJ, Storey County is a 200 MW battery storage request with a signed interconnection agreement in the West interconnection queue, in Storey County, Nevada, connecting to NV Energy.
Queue statusConsented
- PlanningQueued Mar 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- Company NJ
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- Storey County, Nevada
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 30 March 2022
- Proposed online date
- June 2026
Location
Marker shows the centre of Storey County; the queue data does not give exact sites.
Other requests in Storey County
- Gas project 25-00427, Storey CountyGas · 1,000 MW · in study
- Gas project 25-00430, Storey CountyGas · 570 MW · in study
- Gas project 25-00426, Storey CountyGas · 400 MW · in study
- Battery storage project 25-00386, Storey CountyBattery storage · 400 MW · in study
- Battery storage project 25-00431, Storey CountyBattery storage · 250 MW · in study
- Battery storage project 25-00435, Storey CountyBattery storage · 150 MW · in study
- Battery storage project Company NZ, Storey CountyBattery storage · 250 MW · suspended
- Onshore wind project Company NO, Storey CountyOnshore wind · 190 MW · suspended
- Solar + storage project Company NN, Storey CountySolar + storage · 500 MW · withdrawn
- Battery storage project Company KC, Story CountyBattery storage · 300 MW · withdrawn
- Solar + storage project Company KV, Storey CountySolar + storage · 250 MW · withdrawn
- Battery storage project Company NT, Storey CountyBattery storage · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem