United States › Grid › Interconnection queues › Nevada

ONSHORE WIND · WEST

Onshore wind project Company NO, Storey County

Onshore wind project Company NO, Storey County is a 190 MW onshore wind request suspended in the West interconnection queue, in Storey County, Nevada, connecting to NV Energy.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Company NO
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Storey County, Nevada
Technology
Wind: 190 MW
Total requested
190 MW
Service type
NRIS and ERIS
Queue status
Suspended
Entered queue
31 March 2022
Proposed online date
August 2026

Location

Marker shows the centre of Storey County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Storey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem