🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

BATTERY STORAGE · WEST

Battery storage project Company NZ, Storey County

Battery storage project Company NZ, Storey County is a 250 MW battery storage request suspended in the West interconnection queue, in Storey County, Nevada, connecting to NV Energy.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Company NZ
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Storey County, Nevada
Technology
Battery: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Queue status
Suspended
Entered queue
28 September 2022
Proposed online date
December 2030

Location

Marker shows the centre of Storey County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Storey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem