🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

ONSHORE WIND · PJM

Blackford Wind Energy Project

Blackford Wind Energy Project is a 200 MW onshore wind request with a signed interconnection agreement in the PJM interconnection queue, in Blackford County, Indiana, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Sep 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-202
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Keystone-Desoto 345 kV
Location
Blackford County, Indiana
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
25 September 2019
Proposed online date
September 2026

Location

Marker shows the centre of Blackford County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Blackford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem