United States › Grid › Interconnection queues › Minnesota

BATTERY STORAGE · MISO

Battery storage project J3236, Chisago County

Battery storage project J3236, Chisago County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Chisago County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3236
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Chisago County 115kV Substation
Location
Chisago County, Minnesota
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
28 March 2024
Proposed online date
January 2028

Location

Marker shows the centre of Chisago County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Chisago County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem