United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J385, Chisago County
Solar project J385, Chisago County is a 100 MW solar request built and operating in the MISO interconnection queue, in Chisago County, Minnesota.
Request details
- Queue ID
- J385
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Chisago 115 kV Substation
- Location
- Chisago County, Minnesota
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 2 September 2014
- Agreement signed
- 17 October 2016
- Proposed online date
- October 2016
- Came online
- October 2016
Location
Marker shows the centre of Chisago County; the queue data does not give exact sites.
Other requests in Chisago County
- Battery storage project J3236, Chisago CountyBattery storage · 200 MW · in study
- Solar project J3051, Chisago CountySolar · 150 MW · in study
- Surplus; J385Battery storage · 100 MW · in study
- Surplus; J385Other · 100 MW · in study
- Gas project G264, Chisago CountyGas · 905 MW · withdrawn
- Gas project G975, Chisago CountyGas · 855 MW · withdrawn
- Other project G135, Chisago CountyOther · 660 MW · withdrawn
- Other project G236, Chisago CountyOther · 650 MW · withdrawn
- Solar project J1179, Chisago CountySolar · 300 MW · withdrawn
- Battery storage project J3500, Chisago CountyBattery storage · 150 MW · withdrawn
- Solar project J326, Chisago CountySolar · 100 MW · withdrawn
- Solar project J1473, Chisago CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem