Solar project J385, Chisago County

Solar project J385, Chisago County is a 100 MW solar request built and operating in the MISO interconnection queue, in Chisago County, Minnesota.

Queue statusOperating
  1. PlanningQueued Sep 2014 (completed)
  2. ConsentedOct 2016 (completed)
  3. Construction (completed)
  4. OperatingOct 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J385
Grid region
MISO (Midcontinent)
Connection point (POI)
Chisago 115 kV Substation
Location
Chisago County, Minnesota
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
2 September 2014
Agreement signed
17 October 2016
Proposed online date
October 2016
Came online
October 2016

Location

Marker shows the centre of Chisago County; the queue data does not give exact sites.