United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · MISOOnshore wind project J2614, Henry County
Onshore wind project J2614, Henry County is a 200 MW onshore wind request in interconnection study in the MISO interconnection queue, in Henry County, Illinois, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2614
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
- Connection point (POI)
- Mercer 161kV
- Location
- Henry County, Illinois
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- September 2026
Location
Marker shows the centre of Henry County; the queue data does not give exact sites.
Other requests in Henry County
- Onshore wind project J3699, Henry CountyOnshore wind · 300 MW · in study
- Solar project AI2-060, Henry CountySolar · 40.7 MW · in study
- Onshore wind project G545, Henry CountyOnshore wind · 200 MW · built
- Midland Wind FarmOnshore wind · 101 MW · built
- Onshore wind project AE1-193, Henry CountyOnshore wind · 500 MW · withdrawn
- Onshore wind project J101, Henry CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J100, Henry CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project G629, Henry CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project Q60, Henry CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project G544, Henry CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project AA2-039, Henry CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project G701, Henry CountyOnshore wind · 105 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem