United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · PJMMidland Wind Farm
Midland Wind Farm is a 101 MW onshore wind request built and operating in the PJM interconnection queue, in Henry County, Illinois, connecting to ComEd.
Request details
- Queue ID
- AC1-033
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Kewanee 138 kV
- Location
- Henry County, Illinois
- Technology
- Wind: 101 MW
- Total requested
- 101 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 14 August 2016
- Proposed online date
- April 2024
- Came online
- January 2024
Location
Marker shows the centre of Henry County; the queue data does not give exact sites.
Other requests in Henry County
- Onshore wind project J3699, Henry CountyOnshore wind · 300 MW · in study
- Onshore wind project J2614, Henry CountyOnshore wind · 200 MW · in study
- Solar project AI2-060, Henry CountySolar · 40.7 MW · in study
- Onshore wind project G545, Henry CountyOnshore wind · 200 MW · built
- Onshore wind project AE1-193, Henry CountyOnshore wind · 500 MW · withdrawn
- Onshore wind project J101, Henry CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J100, Henry CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project G629, Henry CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project Q60, Henry CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project G544, Henry CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project AA2-039, Henry CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project G701, Henry CountyOnshore wind · 105 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem