Onshore wind project G544, Henry County

Onshore wind project G544, Henry County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Henry County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2005 (completed)
  2. Withdrawn / abandonedMay 2009 (project stopped here)
  3. ConsentedMay 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G544
Grid region
MISO (Midcontinent)
Connection point (POI)
East Kewanee 138 kV Substation
Location
Henry County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
6 September 2005
Agreement signed
4 May 2009
Proposed online date
October 2006
Withdrawn
May 2009

Location

Marker shows the centre of Henry County; the queue data does not give exact sites.