United States › Grid › Interconnection queues › Indiana
SOLAR + STORAGE · PJMSolar + storage project AH2-025, Fountain County
Solar + storage project AH2-025, Fountain County is a 200 MW solar + storage request in interconnection study in the PJM interconnection queue, in Fountain County, Indiana, connecting to AEP.
Queue statusIn planning
- PlanningQueued Oct 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-025
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Eugene - Dequine 345 kV
- Location
- Fountain County, Indiana
- Technology
- Solar: 200 MW · Battery
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 29 October 2021
- Proposed online date
- June 2027
Location
Marker shows the centre of Fountain County; the queue data does not give exact sites.
Other requests in Fountain County
- Solar project J1378, Fountain CountySolar · 200 MW · agreement signed
- Dolphin SolarSolar · 450 MW · in study
- Solar project AG2-163, Fountain CountySolar · 250 MW · in study
- Battery storage project AG2-343, Fountain CountyBattery storage · 100 MW · in study
- Battery storage project AG2-345, Fountain CountyBattery storage · 50.0 MW · in study
- Solar project J2269, Fountain CountySolar · 300 MW · withdrawn
- Solar project AG2-454, Fountain CountySolar · 300 MW · withdrawn
- Onshore wind project J827, Fountain CountyOnshore wind · 300 MW · withdrawn
- Solar project AG2-455, Fountain CountySolar · 280 MW · withdrawn
- Solar project J2805, Fountain CountySolar · 200 MW · withdrawn
- Solar project J1606, Fountain CountySolar · 200 MW · withdrawn
- Solar project J3103, Fountain CountySolar · 145 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem