United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· MISO

Onshore wind project J827, Fountain County

Onshore wind project J827, Fountain County is a 300 MW onshore wind request withdrawn in the MISO interconnection queue, in Fountain County, Indiana, connecting to Duke Energy Corporation.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J827
Grid region
MISO (Midcontinent)
Utility / transmission owner
Duke Energy Corporation
Connection point (POI)
Lafayette - Veedsburg West - Attica 230kV Line
Location
Fountain County, Indiana
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
September 2020
Withdrawn
January 2019

Location

Marker shows the centre of Fountain County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Fountain County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem