United States › Grid › Interconnection queues › Missouri
SOLAR + STORAGE · MISOSolar + storage project J2238, Maries County
Solar + storage project J2238, Maries County is a 200 MW solar + storage request in interconnection study in the MISO interconnection queue, in Maries County, Missouri, connecting to AMEREN MISSOURI.
Queue statusIn planning
- PlanningQueued Jul 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2238
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- The Franks (Bus #300041) - Bland (Bus #344154) 345 kV Line
- Location
- Maries County, Missouri
- Technology
- Solar: 200 MW · Battery
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 16 July 2025
- Proposed online date
- February 2024
Location
Marker shows the centre of Maries County; the queue data does not give exact sites.
Other requests in Maries County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem