United States › Grid › Interconnection queues › Colorado
ONSHORE WIND · WESTOnshore wind project GI-2006-2, Logan County
Onshore wind project GI-2006-2, Logan County is a 200 MW onshore wind request with a signed interconnection agreement in the West interconnection queue, in Logan County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusConsented
- PlanningQueued Jun 2006 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2008 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-2006-2
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Pawnee Substation
- Location
- Logan County, Colorado
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- Feasibility Study Waived System Impact Study and Re- Studies complete Facilities Study complete LGIA draft delayed durin
- Queue status
- Active
- Entered queue
- 9 June 2006
- Proposed online date
- October 2008
Location
Marker shows the centre of Logan County; the queue data does not give exact sites.
Other requests in Logan County
- Onshore wind project GI-2006-1g, Logan CountyOnshore wind · 400 MW · agreement signed
- Onshore wind project GI-2014-4, Logan CountyOnshore wind · 60.0 MW · agreement signed
- Battery storage project GI-SISS-2025-06, Logan CountyBattery storage · 200 MW · in study
- Onshore wind project GI-2025-05, Logan CountyOnshore wind · 75.0 MW · in study
- Onshore wind project GI-2012-3, Logan CountyOnshore wind · 60.0 MW · in study
- Onshore wind project GI-TC-2021-06, Logan CountyOnshore wind · 200 MW · built
- Onshore wind project GI-2013-6, Logan CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GI-2006-4, Logan CountyOnshore wind · 200 MW · withdrawn
- Battery storage project GI-SISS-2025-02, Logan CountyBattery storage · 150 MW · withdrawn
- Onshore wind project GI-2010-5, Logan CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GI-2013-7, Logan CountyOnshore wind · 140 MW · withdrawn