Interconnection queue in the USA — page 101

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 101 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2203, Adams County
Battery storage
150 MWIn study Adams, ILMISO Mar 2022target 2024
Battery storage project IC-1210, Walker County
Battery storage
150 MWAgreement signed Walker, ALSoutheast Dec 2023target 2026
Onshore wind project GI-TC-2024-04, Platte County
Onshore wind
150 MWIn study Platte, WYWest May 2023target 2026
Solar project J1802, Marshall County
Solar
150 MWIn study Marshall, INMISO Jun 2020target 2024
Battery storage project AH2-228, Pickaway County
Battery storage
150 MWIn study Pickaway, OHPJM Mar 2022target 2026
Battery storage project J3009, Washtenaw County
Battery storage
150 MWIn study Washtenaw, MIMISO Aug 2022target 2025
Battery storage project AI2-044, City Of Virginia Beach County
Battery storage
150 MWIn study City Of Virginia Beach, VAPJM Feb 2023target 2023
Solar project J3644, Bay County
Solar
150 MWIn study Bay, MIMISO Apr 2024target 2028
Solar project GI-2024-18, Morgan County
Solar
150 MWIn study Morgan, COWest May 2024target 2027
Solar project J1155, Mississippi County
Solar
150 MWUnder construction Mississippi, ARMISO Mar 20182024
Solar + storage project AG2-126, Vermillion County
Solar + storage · TGE Illinois 211, LLC
150 MWIn study Vermillion, INPJM Mar 2025target 2023
Northdraw Wind
Onshore wind · National Renewable Solutions
150 MWPaused / redesign Randall, TXERCOT Jun 2010target 2020
Onshore wind project GI-TC-2024-08, Kit Carson County
Onshore wind
150 MWAgreement signed Kit Carson, COWest May 2023target 2027
Replacing 150 MW of coal generation with BESS at Lansing; Lansing 4
Battery storage
150 MWIn study Allamakee, IAMISO Apr 2025target 2026
Battery storage project GEN-2025-SR4, Edwards County
Battery storage
150 MWIn study Edwards, KSSPP Aug 2025target 2028
Valcour Storage
Battery storage · Emeren US, LLC
150 MWIn study Clinton, NYNYISO Sep 2024target 2028
Battery storage project J2454, Montcalm County
Battery storage
150 MWIn study Montcalm, MIMISO Sep 2022target 2025
Solar project 18-11071, Larimer County
Solar
150 MWUnder construction Larimer, COWest Nov 2018target 2023
Solar project J3722, Hillsdale County
Solar
150 MWIn study Hillsdale, MIMISO Mar 2024target 2028
Battery storage project J2170, Clark County
Battery storage
150 MWIn study Clark, ILMISO Apr 2022target 2024
Surplus; Shelby
Other
150 MWIn study Cumberland, ILMISO Jun 2024target 2026
Whatley Solar
Solar · Invenergy
150 MWPaused / redesign Andrews, TXERCOT May 2015target 2020
Solar
Solar
150 MWAgreement signed Hartford, CTISO-NE Mar 2022target 2028
Arch 4
Battery storage · Terra-Gen Development Company, LLC
150 MWIn study Orange, NYNYISO Aug 2024target 2028
Solar + storage project GI-2023-173, Imperial County
Solar + storage
150 MWIn study Imperial, CAWest Apr 2023target 2028
Solar + storage project J2897, San Jacinto County
Solar + storage
150 MWIn study San Jacinto, TXMISO Sep 2022target 2025
Solar project GEN-2024-282, Meade County
Solar
150 MWIn study Meade, SDSPP Mar 2025target 2030
Solar project J2501, Goodhue County
Solar
150 MWIn study Goodhue, MNMISO Sep 2022target 2024
Solar project G1001, Grant County
Solar
150 MWIn study Grant, WAWest Nov 2023target 2029
Solar project J1096, Saline County
Solar
150 MWUnder construction Saline, ILMISO Mar 2018target 2024
Solar + storage project GEN-2024-117, Washington County
Solar + storage
150 MWIn study Washington, OKSPP Mar 2025target 2028
Other project ERAS-2025-031, Wyandotte County
Other
150 MWIn study Wyandotte, KSSPP Oct 2025target 2028
Lincoln Park DG, LLC
Battery storage · BayWa r.e Projects LLC.
150 MWIn study Ulster, NYNYISO Aug 2024target 2030
CPV Capon Springs Wind
Onshore wind · CPV Springs Wind, LLC
150 MWIn study Hampshire, WVPJM Jan 2025target 2025
Onshore wind project J967, Mower County
Onshore wind
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Solar + storage project Company 168, Clark County
Solar + storage
150 MWAgreement signed Clark, NVWest Sep 2018target 2026
Big Pine Solar
Solar
150 MWAgreement signed Sussex, VAPJM Feb 2019target 2031
Solar + storage project 538, Henderson County
Solar + storage
150 MWAgreement signed Henderson, TNSoutheast Mar 2023target 2029
Battery storage project 102, Thurston County
Battery storage
150 MWPaused / redesign Thurston, WAWest Apr 2021target 2028
Battery storage project 22-111, Multnomah County
Battery storage
150 MWIn study Multnomah, ORWest Nov 2022target 2028
Solar project J2720, Yazoo County
Solar
150 MWIn study Yazoo, MSMISO Sep 2022target 2025
Solar project J2314, Liberty County
Solar
150 MWIn study Liberty, TXMISO Sep 2021target 2023
Gemstone Solar
Solar
150 MWAgreement signed Cass, MIPJM Jan 2020target 2028
Solar project J2156, Johnson County
Solar
150 MWIn study Johnson, ILMISO Jun 2022target 2024
Peregrine BESS 2
Solar + storage · CED Development Inc.
150 MWIn study Goliad, TXERCOT Aug 2022target 2027
Solar project GI-2023-170, Imperial County
Solar
150 MWIn study Imperial, CAWest Apr 2023target 2026
Battery storage project J3695, Clark County
Battery storage
150 MWIn study Clark, ILMISO Apr 2024target 2028
Solar + storage project IC-1099, Pulaski County
Solar + storage
150 MWPaused / redesign Pulaski, GASoutheast Nov 2022target 2026
Nickel Spruce Solar
Solar · Nickel Spruce Solar LLC
150 MWIn study Leon, TXERCOT Jan 2023target 2027
Solar project J874, Murray County
Solar
150 MWUnder construction Murray, MNMISO Jun 2017target 2024
Page 101 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)