🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Colorado

SOLAR · WEST

Solar project 18-11071, Larimer County

Solar project 18-11071, Larimer County is a 150 MW solar request under construction in the West interconnection queue, in Larimer County, Colorado, connecting to Platte River Power Authority.

Queue statusUnder construction
  1. PlanningQueued Nov 2018 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingTarget Jan 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
18-11071
Grid region
West (non-ISO utilities)
Utility / transmission owner
Platte River Power Authority
Connection point (POI)
Ault-Carey 230kV
Location
Larimer County, Colorado
Technology
Solar: 150 MW
Total requested
150 MW
Study phase
Construction
Queue status
Active
Entered queue
7 November 2018
Proposed online date
January 2023

Location

Marker shows the centre of Larimer County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Larimer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem