Solar project 25-041825, Larimer County

Solar project 25-041825, Larimer County is a 50.0 MW solar request in interconnection study in the West interconnection queue, in Larimer County, Colorado, connecting to Platte River Power Authority.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25-041825
Grid region
West (non-ISO utilities)
Utility / transmission owner
Platte River Power Authority
Connection point (POI)
Rawhide 34.5kV
Location
Larimer County, Colorado
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
18 April 2025
Proposed online date
December 2028

Location

Marker shows the centre of Larimer County; the queue data does not give exact sites.