Onshore wind project 17-07183, Larimer County

Onshore wind project 17-07183, Larimer County is a 100 MW onshore wind request built and operating in the West interconnection queue, in Larimer County, Colorado, connecting to Platte River Power Authority.

Queue statusOperating
  1. PlanningQueued Jul 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
17-07183
Grid region
West (non-ISO utilities)
Utility / transmission owner
Platte River Power Authority
Connection point (POI)
Rawhide 230kV
Location
Larimer County, Colorado
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
18 July 2017
Proposed online date
December 2020

Location

Marker shows the centre of Larimer County; the queue data does not give exact sites.