United States › Grid › Interconnection queues › Colorado

SOLAR · WEST

Solar project 20-02261, Larimer County

Solar project 20-02261, Larimer County is a 100 MW solar request in interconnection study in the West interconnection queue, in Larimer County, Colorado, connecting to Platte River Power Authority.

Queue statusIn planning
  1. PlanningQueued Feb 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
20-02261
Grid region
West (non-ISO utilities)
Utility / transmission owner
Platte River Power Authority
Connection point (POI)
Ault-Carey 230kV
Location
Larimer County, Colorado
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
System Impact Study
Queue status
Active
Entered queue
26 February 2020
Proposed online date
January 2023

Location

Marker shows the centre of Larimer County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Larimer County