United States › Grid › Interconnection queues › California
SOLAR + STORAGE · WESTSolar + storage project GI-2023-173, Imperial County
Solar + storage project GI-2023-173, Imperial County is a 150 MW solar + storage request in interconnection study in the West interconnection queue, in Imperial County, California, connecting to Imperial Irrigation District.
- PlanningQueued Apr 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-2023-173
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Imperial Irrigation District
- Connection point (POI)
- 230kV Sinclair Sub
- Location
- Imperial County, California
- Technology
- Solar: 150 MW · Battery
- Total requested
- 150 MW
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 28 April 2023
- Proposed online date
- June 2028
Location
Marker shows the centre of Imperial County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Imperial County
- UmbrielSolar + storage · 2,365 MW · agreement signed
- Silver Ridge Mount SignalSolar + storage · 750 MW · agreement signed
- Kingsley Solar FarmSolar + storage · 720 MW · agreement signed
- Ocotillo ExpressWind + storage · 504 MW · agreement signed
- Big Rock Solar FarmBattery storage · 200 MW · agreement signed
- Sunrise ButteSolar + storage · 150 MW · agreement signed
- Leconte Energy StorageBattery storage · 125 MW · agreement signed
- Solar + storage project GI-2022-164, Imperial CountySolar + storage · 800 MW · in study
- Yuha Desert Battery StorageBattery storage · 633 MW · in study
- Solar + storage project GI-2023-167, Imperial CountySolar + storage · 500 MW · in study
- Battery storage project GI-2023-168, Imperial CountyBattery storage · 387 MW · in study
- Solar + storage project GI-2022-162, Imperial CountySolar + storage · 270 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem