BATTERY STORAGE · WESTBattery storage project 102, Thurston County
Battery storage project 102, Thurston County is a 150 MW battery storage request suspended in the West interconnection queue, in Thurston County, Washington, connecting to Puget Sound Energy.
- PlanningQueued Apr 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 102
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Puget Sound Energy
- Connection point (POI)
- St. Clair 230 kV Substation
- Location
- Thurston County, Washington
- Technology
- Battery: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Suspended LGIA
- Queue status
- Suspended
- Entered queue
- 15 April 2021
- Proposed online date
- September 2028
Location
Marker shows the centre of Thurston County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Thurston County
- Battery storage project 112, Thurston CountyBattery storage · 127 MW · agreement signed
- Wind + storage project G0921, Thurston CountyWind + storage · 718 MW · in study
- Other project 141, Thurston CountyOther · 300 MW · in study
- Battery storage project G0830, Thurston CountyBattery storage · 20.0 MW · in study
- Battery storage project G0942, Thurston CountyBattery storage · 20.0 MW · in study
- Solar project 53, Thurston CountySolar · 198 MW · withdrawn
- Battery storage project 132, Thurston CountyBattery storage · 127 MW · withdrawn
- Solar project 63, Thurston CountySolar · 105 MW · withdrawn
- Battery storage project 82, Thurston CountyBattery storage · 100 MW · withdrawn
- Battery storage project 134, Thurston CountyBattery storage · 100 MW · withdrawn
- Battery storage project 118, Thurston CountyBattery storage · 100 MW · withdrawn
- Battery storage project 89, Thurston CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem