United States βΊ Grid βΊ Interconnection queues βΊ Washington
SOLAR Β· WESTSolar project 53, Thurston County
Solar project 53, Thurston County is a 198 MW solar request withdrawn in the West interconnection queue, in Thurston County, Washington, connecting to Puget Sound Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2017 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 53
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Puget Sound Energy
- Connection point (POI)
- Tono-Olympia 115kV Line, Tono-Tenino 115kV line & Tono substation
- Location
- Thurston County, Washington
- Technology
- Solar: 198 MW
- Total requested
- 198 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 17 October 2017
- Proposed online date
- October 2019
Location
Marker shows the centre of Thurston County; the queue data does not give exact sites.
Power plants in Washington Β· Transmission lines in Washington
Other requests in Thurston County
- Battery storage project 112, Thurston CountyBattery storage Β· 127 MW Β· agreement signed
- Wind + storage project G0921, Thurston CountyWind + storage Β· 718 MW Β· in study
- Other project 141, Thurston CountyOther Β· 300 MW Β· in study
- Battery storage project G0830, Thurston CountyBattery storage Β· 20.0 MW Β· in study
- Battery storage project G0942, Thurston CountyBattery storage Β· 20.0 MW Β· in study
- Battery storage project 102, Thurston CountyBattery storage Β· 150 MW Β· suspended
- Battery storage project 132, Thurston CountyBattery storage Β· 127 MW Β· withdrawn
- Solar project 63, Thurston CountySolar Β· 105 MW Β· withdrawn
- Battery storage project 82, Thurston CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project 134, Thurston CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project 118, Thurston CountyBattery storage Β· 100 MW Β· withdrawn
- Battery storage project 89, Thurston CountyBattery storage Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem