Other project 141, Thurston County

Other project 141, Thurston County is a 300 MW other request in interconnection study in the West interconnection queue, in Thurston County, Washington, connecting to Puget Sound Energy.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
141
Grid region
West (non-ISO utilities)
Utility / transmission owner
Puget Sound Energy
Connection point (POI)
Tono 115kV Substation
Location
Thurston County, Washington
Technology
Solar: 300 MW · Wind · Battery
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Transitional Cluster Study
Queue status
Active
Entered queue
16 February 2024
Proposed online date
November 2030

Location

Marker shows the centre of Thurston County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Thurston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem