Gemstone Solar

Gemstone Solar is a 150 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Cass County, Michigan, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Jan 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-083
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Kenzie Creek-Stone Lake 69 kV
Location
Cass County, Michigan
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
31 January 2020
Proposed online date
December 2028

Location

Marker shows the centre of Cass County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan