Solar project AI2-215, Cass County

Solar project AI2-215, Cass County is a 18.1 MW solar request in interconnection study in the PJM interconnection queue, in Cass County, Michigan, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI2-215
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Pokagon - Corey 69 kV
Location
Cass County, Michigan
Technology
Solar: 18.1 MW
Total requested
18.1 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
2 March 2023
Proposed online date
March 2026

Location

Marker shows the centre of Cass County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Cass County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem