United States βΊ Grid βΊ Interconnection queues βΊ Michigan
SOLAR Β· PJMWingstem Solar Energy Farm
Wingstem Solar Energy Farm is a 150 MW solar request suspended in the PJM interconnection queue, in Cass County, Michigan, connecting to AEP.
Queue statusPaused / redesign
- PlanningQueued Sep 2018 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AE1-170
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Kenzie Creek-Colby 138 kV
- Location
- Cass County, Michigan
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 25 September 2018
- Proposed online date
- December 2025
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
- Gemstone SolarSolar Β· 150 MW Β· agreement signed
- Solar project J4102, Cass CountySolar Β· 539 MW Β· in study
- Cass County SolarSolar + storage Β· 200 MW Β· in study
- Battery storage project AI1-166, Cass CountyBattery storage Β· 150 MW Β· in study
- Solar project AI2-169, Cass CountySolar Β· 24.0 MW Β· in study
- Solar project AI2-215, Cass CountySolar Β· 18.1 MW Β· in study
- Indeck Niles Energy CenterGas Β· 994 MW Β· built
- Indeck Niles Energy CenterGas Β· 91.0 MW Β· built
- Onshore wind project J1075, Cass CountyOnshore wind Β· 350 MW Β· withdrawn
- Onshore wind project J1077, Cass CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project V4-016, Cass CountyOnshore wind Β· 200 MW Β· withdrawn
- Solar project AF2-390, Cass CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem