United States › Grid › Interconnection queues › Michigan
GAS · PJMIndeck Niles Energy Center
Indeck Niles Energy Center is a 91.0 MW gas request built and operating in the PJM interconnection queue, in Cass County, Michigan, connecting to AEP.
Request details
- Queue ID
- AC1-141
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Cook-East Elkhart 345kV
- Location
- Cass County, Michigan
- Technology
- Gas: 91.0 MW
- Total requested
- 91.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 28 October 2016
- Proposed online date
- March 2022
- Came online
- December 2021
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
- Gemstone SolarSolar · 150 MW · agreement signed
- Solar project J4102, Cass CountySolar · 539 MW · in study
- Cass County SolarSolar + storage · 200 MW · in study
- Battery storage project AI1-166, Cass CountyBattery storage · 150 MW · in study
- Solar project AI2-169, Cass CountySolar · 24.0 MW · in study
- Solar project AI2-215, Cass CountySolar · 18.1 MW · in study
- Wingstem Solar Energy FarmSolar · 150 MW · suspended
- Indeck Niles Energy CenterGas · 994 MW · built
- Onshore wind project J1075, Cass CountyOnshore wind · 350 MW · withdrawn
- Onshore wind project J1077, Cass CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project V4-016, Cass CountyOnshore wind · 200 MW · withdrawn
- Solar project AF2-390, Cass CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem