πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· PJM

Onshore wind project V4-016, Cass County

Onshore wind project V4-016, Cass County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Cass County, Michigan, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2009 (completed)
  2. Withdrawn / abandonedMar 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
V4-016
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Valley 138kV
Location
Cass County, Michigan
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
25 November 2009
Proposed online date
November 2014
Withdrawn
March 2015

Location

Marker shows the centre of Cass County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Cass County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem