United States › Grid › Interconnection queues › Tennessee
SOLAR + STORAGE · SOUTHEASTSolar + storage project 538, Henderson County
Solar + storage project 538, Henderson County is a 150 MW solar + storage request with a signed interconnection agreement in the Southeast interconnection queue, in Henderson County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusConsented
- PlanningQueued Mar 2023 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Apr 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 538
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Connection point (POI)
- Johnsonville Steam - Chesterfield 161-kV TL
- Location
- Henderson County, Tennessee
- Technology
- Solar: 150 MW · Battery
- Total requested
- 150 MW
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 28 March 2023
- Proposed online date
- April 2029
Location
Marker shows the centre of Henderson County; the queue data does not give exact sites.
Other requests in Henderson County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem