🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J3722, Hillsdale County

Solar project J3722, Hillsdale County is a 150 MW solar request in interconnection study in the MISO interconnection queue, in Hillsdale County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3722
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
COLDWATER - MOORE ROAD 138.0kV
Location
Hillsdale County, Michigan
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
27 March 2024
Proposed online date
September 2028

Location

Marker shows the centre of Hillsdale County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Hillsdale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem