πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project J056, Hillsdale County

Onshore wind project J056, Hillsdale County is a 101 MW onshore wind request withdrawn in the MISO interconnection queue, in Hillsdale County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2009 (completed)
  2. Withdrawn / abandonedJun 2013 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J056
Grid region
MISO (Midcontinent)
Connection point (POI)
Litchfield - Coldwater 138kV
Location
Hillsdale County, Michigan
Technology
Wind: 101 MW
Total requested
101 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
27 July 2009
Agreement signed
13 July 2012
Proposed online date
July 2012
Withdrawn
June 2013

Location

Marker shows the centre of Hillsdale County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Hillsdale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem