United States › Grid › Interconnection queues › Michigan

ONSHORE WIND · MISO

Onshore wind project J2283, Hillsdale County

Onshore wind project J2283, Hillsdale County is a 16.1 MW onshore wind request in interconnection study in the MISO interconnection queue, in Hillsdale County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Nov 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2020 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2283
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
18Knowles (MISO node #256632)
Location
Hillsdale County, Michigan
Technology
Wind: 16.1 MW
Total requested
16.1 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
19 November 2021
Proposed online date
October 2020

Location

Marker shows the centre of Hillsdale County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Hillsdale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem