United States › Grid › Interconnection queues › Michigan
ONSHORE WIND · MISOOnshore wind project J2283, Hillsdale County
Onshore wind project J2283, Hillsdale County is a 16.1 MW onshore wind request in interconnection study in the MISO interconnection queue, in Hillsdale County, Michigan, connecting to METC.
Queue statusIn planning
- PlanningQueued Nov 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2020 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2283
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- 18Knowles (MISO node #256632)
- Location
- Hillsdale County, Michigan
- Technology
- Wind: 16.1 MW
- Total requested
- 16.1 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 19 November 2021
- Proposed online date
- October 2020
Location
Marker shows the centre of Hillsdale County; the queue data does not give exact sites.
Other requests in Hillsdale County
- Solar project J1658, Hillsdale CountySolar · 180 MW · agreement signed
- Solar project J3722, Hillsdale CountySolar · 150 MW · in study
- Solar project J2812, Hillsdale CountySolar · 140 MW · in study
- Onshore wind project J538, Hillsdale CountyOnshore wind · 150 MW · built
- Onshore wind project G766, Hillsdale CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J085, Hillsdale CountyOnshore wind · 150 MW · withdrawn
- Solar project J846, Hillsdale CountySolar · 140 MW · withdrawn
- Onshore wind project J056, Hillsdale CountyOnshore wind · 101 MW · withdrawn
- Solar project J1555, Hillsdale CountySolar · 100 MW · withdrawn
- Solar + storage project J2119, Hillsdale CountySolar + storage · 50.0 MW · withdrawn
- Onshore wind project J099, Hillsdale CountyOnshore wind · 48.6 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem